Fortescue Zero

THE CHALLENGE

Fortescue Zero needed a dust containment wall within their factory so that they could begin the production of batteries whilst continuing civil and building works in another area of the factory over a period of months.

THE SOLUTION

Durascreen® was recommended in PX 1000 for containment of dust.

Features included to meet specific need:

  • Inbuilt 10T wind restraint straps.
  • Foam infills between purlins to ensure containment of dust, fumes, and odours.
  • 3x rapid doors to enable free movement of forklift trucks and materials.
  • 3x pedestrian doors adjacent to the rapid doors to enable safe passage of pedestrians via pedestrian walkways.
  • A dual colour screen was requested for aesthetic purposes with a blue base and white to the ceiling.

MORE DETAILS

Installation duration: 15 days
Size: L 76m x H 17.8m
Market Category: Battery Manufacturing
Fabric type: PX1000

Image Gallery