Overbury
THE PROBLEM
Overbury needed temporary walling to contain dust on site whilst sandblasting a brick wall they wanted to return to face-brickwork
Wall was needed at short notice and needed to have ability for dust and odour extraction systems to be installed through the wall
THE SOLUTION
Durascreen was recommended in our PX520 fabric in yellow.
Specific elements included to meet Overbury’s requirements:
- V-overlap joining system to contain dust
- Foam infills to ensure a dust-tight seal
- Durascreen draw-aside curtain with cleats to fasten it closed when not in use
MORE DETAILS
Installation duration: 3 Days
Size: W51m x H6.8m
Product used: PX520 Fabric
Market Category: Corporate / Commercial refurbishment
CLIENT TESTIMONIAL
Image Gallery